AIRAC 2611 - LIRN - Runway 05/23 appeared (and linked to procedures) too early in time

Hello guys,

please check the released airac for LIRN airport.

have appeared now the runways 05/23 in parallel to 06/24 (too early, they will change in th future months… not now). Due to this now all procedures are linked to those wrong runways not corresponding to the actually existing 06/24.

Hi,
Sorry for the delay in responding; I was too busy with the AIRAC release over the last couple of days to analyze your post in detail.

The changes were officially announced in September 2026, well before the effective date of AIRAC 2611. I have checked the AIP Italy (ENAV) and have tried to provide a short history of this change:

  • 17 September 2026: Publication of trigger NOTAM A4869/26, announcing AIRAC Supplement S60/26
  • 29 October 2026: AIRAC cycle 2611 becomes effective
  • 1 November 2026: Start of the runway rehabilitation project and the validity period of Supplement S60/26
  • 22 November 2026: Estimated end of the initial runway closure under NOTAM A5846/26
  • 26 November 2026: AIRAC cycle 2612 becomes effective
  • 23 December 2026: Scheduled end of the Supplement S60/26 validity period

So, the runway redesignation was officially published before AIRAC 2611 took effect, and Jeppesen appears to have incorporated the planned runway configuration and associated terminal procedure changes into AIRAC 2611, based on the published Italian AIS information.

At least for me, this is understandable from a navigation database perspective, as runway redesignations may require corresponding changes to:

  • Airport and runway identifiers
  • Runway-related navigation database records
  • SID and STAR runway transitions, where applicable
  • Instrument approach procedures and their runway references
  • ILS/DME-related navigation data

Consequently, the new runway designations and associated terminal procedures can already appear in the AIRAC 2611 navigation database, even though the physical runway rehabilitation and the operational transition are still in progress.

But, and that is important now, I guess:

  1. Notam A5846/25 declares runway 06/24 closed due to WIP. Valid from 01. November to 22.November 2026
A5846/26 NOTAMN
Q) LIRR/QMRLC/IV/NBO/A /000/999/4053N01417E005
A) LIRN B) 2611010000 C) 2611222359EST
E) RWY 06/24 CLSD DUE TO WIP
REF AIP SUP S60/26-PHASE 1 AND NOTAM A5706/26
  1. Notams A5835/26 declares DME NPC associated with ILS 06 as unavailable
A5835/26 NOTAMN
Q) LIRR/QIDAS/I /NBO/A /000/999/4053N01417E005
A) LIRN B) 2611010000 C) 2611302359EST
E) DME 'NPC', ASSOCIATED WITH ILS RWY06, NOT AVAILABLE.
REF AIP SUP S60/26-PHASE 1
  1. Notam A5836/26 declares DME NAP associated with ILS 24 as unavailable
A5836/26 NOTAMN
Q) LIRR/QIDAS/I /NBO/A /000/999/4053N01417E005
A) LIRN B) 2611010000 C) 2611302359EST
E) DME 'NAP', ASSOCIATED WITH ILS RWY24, NOT AVAILABLE.
REF AIP SUP S60/26-PHASE 1

Therefore, the inclusion of Runway 05/23 and the corresponding terminal procedures in AIRAC 2611 is consistent with the previously announced runway redesignation at LIRN.

It therefore does not, by itself, indicate an error in the Jeppesen navigation database.

Hope that helps a little bit